Concrete Volume Calculator

Enter the size of your slab, floor or footing to get concrete volume, cement bags, sand and stone.

Prefer us on Google

Results update as you type. Thickness is in inches with feet, and in millimeters with meters.

Concrete needed, including wastage

131.25ft³

Same as 3.72 m³ and 4.86 yd³

Cement
24 bags50 kg each, about 1,200 kg
Sand
57.8 ft³1.64 m³
Stone (aggregate)
115.5 ft³3.27 m³
  • Free to use
  • Feet or meters
  • Working shown
  • Made for phones
Prefer us on Google

How we calculated it

The tool multiplies your three sizes to get the wet volume, adds wastage, then splits the dry volume by your mix. Each step below uses your numbers.

What you measure

A concrete slab with length, width and thickness marked L Length W Width T Thickness
Take length and width from the plan or the fixed formwork. Take thickness from the slab depth.
Volume = L × W × T × Quantity

Your mix at a glance

Cement 1 part, sand 2 parts, stone 4 parts

SymbolMeaningUnit
L, WLength and widthft or m
TThicknessin or mm
QuantityIdentical slabsnumber
WastageExtra for spillagepercent
1.54Dry volume factorfixed
28.850 kg bags per m³ of cementfixed
  1. 1. Wet volume

    Volume = Length × Width × Thickness × Quantity

  2. 2. Add wastage

    Volume with wastage = Volume × (1 + Wastage ÷ 100)

  3. 3. Dry volume

    Dry volume = Volume with wastage × 1.54

  4. 4. Share of each material

    Cement = Dry volume × Cement part ÷ Total parts

  5. 5. Cement bags

    Bags = Cement volume × 28.8, rounded up

Thickness is converted to feet or meters first. The number 28.8 comes from a cement density of 1,440 kg per cubic meter divided by a 50 kg bag. Sand and stone use the same share formula as cement.

Worked examples

Four common jobs. Press Load in calculator to try the sizes and change them to match your site.

Roof slab for a 12 by 14 ft room

12 ft × 14 ft × 5 in, wastage 5 percent, mix 1:2:4

Concrete
73.50 ft³
Cement
14 bags
Sand
32.3 ft³
Stone
64.7 ft³

A bedroom roof with a short span. Five inches is a common thickness for it.

Driveway, 30 by 10 ft

30 ft × 10 ft × 4 in, wastage 5 percent, mix 1:2:4

Concrete
105.00 ft³
Cement
19 bags
Sand
46.2 ft³
Stone
92.4 ft³

A single car driveway on a compacted base. Four inches suits light vehicles.

Store room floor, 6 by 4 m

6 m × 4 m × 100 mm, wastage 5 percent, mix 1:2:4

Concrete
2.52 m³
Cement
16 bags
Sand
1.11 m³
Stone
2.22 m³

A ground floor slab measured in meters, with thickness in millimeters.

Two balcony slabs, 8 by 4 ft

8 ft × 4 ft × 6 in, 2 slabs, wastage 5 percent, mix 1:1.5:3

Concrete
33.60 ft³
Cement
8 bags
Sand
14.1 ft³
Stone
28.2 ft³

Balconies carry more load, so this one uses a stronger mix and six inches.

Why use this calculator

Here is how it compares with a basic volume calculator.

What you getConstructlifyBasic calculators
Feet and metersBoth, values convertOften one unit
Working shownFive steps, your numbersFinal number only
WastageYou set 0 to 50 percentFixed or missing
Mix ratioFour common ratiosOne fixed mix
CementWhole 50 kg bagsOften a decimal
On a phoneResult in viewBuilt for desktop

Feet or meters

Switch units with one tap. Your values convert for you.

Materials split

Cement bags, sand and stone for the mix you choose.

Working shown

Every step uses your numbers, so nothing is hidden.

Adjustable wastage

Set it for your ground and your formwork.

Copy the result

Send the numbers to your supplier or your team.

Made for phones

Large inputs and a result you can read on site.

Quick reference tables

GradeRatioCommon useBags per m³
M101:3:6Plain concrete under foundations4.4
M151:2:4Floors and ordinary slabs6.3
M201:1.5:3Roof slabs, beams and columns8.1
M251:1:2Heavily loaded members11.1

Bags are 50 kg per cubic meter of wet concrete. Your drawing decides the grade.

Concrete volume calculation guide

What this calculator does

This calculator works out how much concrete a slab, floor, footing or beam needs, and how much cement, sand and stone go into it. You enter the length, width, thickness, wastage and mix. It returns the volume in cubic feet, cubic meters and cubic yards.

How to measure the job

Measure length and width in feet or meters, and thickness in inches or millimeters. Take the sizes from the fixed formwork when you can. For a beam, use the span as length, the beam width as width and the depth as thickness.

Why wastage matters

Ground is never perfectly level and formwork moves under load. Five percent covers most flat slabs, and footings in soft soil can need up to ten percent.

From concrete volume to cement bags

Wet concrete shrinks when water fills the gaps between dry particles, so the dry materials take up about 1.54 times the wet volume. The calculator multiplies your volume by 1.54, splits it by the mix parts, and converts the cement share into 50 kg bags. Bags round up to a whole number, so you never plan to buy a part bag.

Before you order

Check the formwork once more on the day and keep two spare bags. Ask your supplier about minimum loads and delivery time. Confirm structural work with your engineer, and see the concrete and cement calculators for the next stage.

What builders say

These are sample reviews for the design preview. Replace them with real reviews from your users before launch.

I checked a 1,200 sq ft roof pour here before calling the supplier. The bag count matched my estimate, and the working steps made it easy to show the owner.
Hamza R.Site supervisor, LahoreSample
I had no idea how many cubic feet my driveway needed. I typed in the sizes and had a number in seconds. The examples helped me trust it.
Ayesha M.Homeowner, KarachiSample
Good for slab and footing homework. I would like round column support, but the formula section explains the dry volume factor better than my textbook.
Daniel K.Civil engineering student, NairobiSample
Drawings from different clients come in feet or meters. Switching units without retyping saves time, and I paste the copied result straight into WhatsApp.
Bilal A.Contractor, IslamabadSample
I use it for quick quantity checks before a full estimate. Wastage is adjustable, which matters because our footings never come out perfect.
Sarah T.Estimator, ManchesterSample
Clear on my phone while standing on site. Big inputs and a big result. A saved history would be nice, though the copy button covers most of it.
Usman Q.Site engineer, DubaiSample
Used it for a small garage floor. The bar showing cement, sand and stone parts helped my helper understand the batching.
Maria L.Renovation planner, TorontoSample
Simple and honest. It shows the 1.54 factor and where 28.8 comes from, so I could check the sum by hand.
Tariq H.Mason, FaisalabadSample

Frequently asked questions

How do I calculate concrete for a slab?

Multiply length by width by thickness, with thickness changed to the same unit as the length. A slab 20 ft long, 15 ft wide and 5 inches thick is 20 × 15 × (5 ÷ 12) = 125 cubic feet. Add about 5 percent for wastage.

How much concrete do I need for a 10 by 10 ft slab that is 4 inches thick?

The plain volume is 10 × 10 × (4 ÷ 12) = 33.3 cubic feet, or 1.23 cubic yards. With 5 percent wastage, plan for 35 cubic feet, which is about 1.30 cubic yards.

How many bags of cement do I need for a 10 by 10 ft slab, 4 inches thick?

With a 1:2:4 mix and 5 percent wastage, the slab needs about 6.3 bags, so buy 7 bags of 50 kg. Add a spare bag if the base is uneven.

How many bags of cement are in 1 cubic meter of concrete?

It depends on the mix. A 1:2:4 mix needs about 6.3 bags of 50 kg, a 1:1.5:3 mix needs about 8.1 bags, and a 1:3:6 mix needs about 4.4 bags.

What is the best mix ratio for a roof slab?

Most roof slabs use M20, which is 1:1.5:3, unless the structural drawing says otherwise. The drawing and your engineer decide the grade. This calculator only helps you work out the quantities.

How much wastage should I add to a concrete order?

Five percent is normal for a flat slab on a level base. Footings in soft soil or uneven trenches can need 7 to 10 percent, because the ground takes more concrete than the plan shows.

Why is the dry volume 1.54 times the wet volume?

Dry cement, sand and stone have gaps between them. Water and mixing fill those gaps and the batch shrinks. Site engineers use 1.54 for this, and some use 1.57 for a little extra margin.

How many cubic feet are in a cubic meter and a cubic yard?

One cubic meter is 35.3147 cubic feet. One cubic yard is 27 cubic feet, so one cubic meter is about 1.308 cubic yards.

How much does a cubic meter of concrete weigh?

About 2,400 kg, which is roughly 150 pounds per cubic foot. Use this figure when you plan truck loads, pumps and the strength of temporary supports.

How much concrete do I need for a 1,000 sq ft roof slab?

At 5 inches thick, 1,000 × (5 ÷ 12) = 417 cubic feet. That is 15.4 cubic yards or 11.8 cubic meters before wastage.

Can I use this calculator for beams and columns?

Yes, for rectangular members. Enter the span or height as length, the member width as width, the depth as thickness, and the number of members as quantity. Round columns need the area of a circle instead.

From the blog

All articles

How to measure a slab so you do not order short

Most short orders come from measuring the plan and forgetting the site. Measure the formwork, not the drawing.

Read the full article

Take length and width from the fixed formwork, because it shows what the pour will really hold. Measure at three places along each side, since shuttering bows and ground level changes.

Use the average thickness, and check it near beams and edges where the slab usually runs deeper.

Keep every size in one unit. Feet with inches is the usual trap, because 5 inches is 0.4167 feet and not 0.5. Here you enter inches as inches and the conversion is done for you.

Ready mix or site mix: which costs less?

Small pours can be mixed on site. Larger pours usually go to ready mix. Compare total cost, not only price per cubic meter.

Read the full article

Below about 1 to 2 cubic meters (35 to 70 cubic feet), a site mixer is usually fine. You need cement, sand, stone, water, a mixer and a crew of four to six people.

Above that, ready mix often wins. The grade is consistent and the pour finishes faster. Check the supplier's minimum load, delivery charge and waiting time, and add labour and mixer hire to the site mix cost before you compare.

Concrete must be placed within the time your supplier gives you, often around 90 minutes and less in hot weather. Have the crew and formwork ready first.

Five mistakes that waste concrete

Most waste comes from five small habits. All of them are easy to fix before the truck arrives.

Read the full article

1. Mixing units. Length in feet with thickness in inches gives a wrong volume unless you convert it.

2. Skipping wastage. A plan volume is a minimum, and the real pour is always a little bigger.

3. Buying materials equal to the wet volume. Dry cement, sand and stone need about 1.54 times the wet volume.

4. Rounding bags down. Buy whole bags and round up.

5. Pouring onto dry soil. The ground absorbs water from the mix and weakens the surface, so wet the base before the pour.