How to measure tube forms
Read the guide
Measure across the inside of the tube and record the fill depth. Group identical tubes together. Confirm the planned bottom and top elevations before ordering.
Estimate the concrete for rectangular, round and tube formed footings using your project dimensions.
The working below updates as you change the footing shape and dimensions.
| Input | What to enter | Units |
|---|---|---|
| Length | Length of a straight rectangular section | ft |
| Width or diameter | Inside size of the form | in |
| Depth | Actual concrete fill depth | in |
| Quantity | Number with identical dimensions | whole number |
| Wastage | Extra for your site conditions | % |
| Bag yield | Volume of mixed concrete per bag | ft³ |
Width, diameter and depth in inches ÷ 12
Rectangle = length × width. Circle = π × radius².
Footprint area × depth × quantity
Base volume × (1 + wastage ÷ 100). Divide ft³ by 27 to get yd³.
Adjusted ft³ ÷ yield per bag, rounded up
Wastage is applied once. Bag counts use the unrounded volume.
Select Load in calculator to try any example.
40 ft long × 16 in wide × 8 in deep, 1 footing(s), 10% wastage
Illustrative dimensions only. Use your project’s plan and measured form sizes.
2 ft long × 24 in wide × 12 in deep, 4 footing(s), 5% wastage
Illustrative dimensions only. Use your project’s plan and measured form sizes.
12 in inside diameter × 36 in deep, 6 footing(s), 10% wastage
Illustrative dimensions only. Use your project’s plan and measured form sizes.
24 in inside diameter × 12 in deep, 2 footing(s), 0% wastage
Illustrative dimensions only. Use your project’s plan and measured form sizes.
| What you get | Constructlify | Manual calculation |
|---|---|---|
| Units | Enter feet and inches directly | Convert before multiplying |
| Shapes | Rectangular and round modes | Choose the formula yourself |
| Wastage | Applied once to the measured volume | Add separately |
| Premix bags | Preset or custom yield and whole bags | Divide and round up yourself |
Read results in cubic yards and cubic feet.
Estimate rectangular sections or round tubes.
Follow each calculation using your inputs.
Set the allowance for your job.
Copy yards, feet and bag count.
Use the calculator while measuring.
| Premix bag | Example yield |
|---|---|
| 40 lb | 0.3 ft³ |
| 50 lb | 0.375 ft³ |
| 60 lb | 0.45 ft³ |
| 80 lb | 0.6 ft³ |
| 90 lb | 0.675 ft³ |
QUIKRETE Concrete Mix data sheet. Use the label on the mix you actually buy.
| Shape | Measure |
|---|---|
| Strip or pad | Inside length, width and fill depth |
| Round or tube form | Inside diameter and fill depth |
| Stepped or belled | Measure separate portions without double counting |
Use supplied dimensions from the project plans.
| From | To |
|---|---|
| 12 inches | 1 foot |
| 27 cubic feet | 1 cubic yard |
| 1 cubic foot | 1,728 cubic inches |
The calculator converts all dimensions to feet before finding volume.
For a strip or pad, measure the inside length and width of the form and the concrete depth. For a tube, use its inside diameter and the planned fill depth. The tube may be taller than the part you intend to fill.
Divide stepped runs into blocks with consistent widths and depths. At corners or intersections, count the shared volume once. For a pier over a wider pad, count the shaft above the pad separately from the pad itself.
Base volume is the measured space to fill. Your allowance accounts for site conditions such as uneven excavation and spillage. Measure the forms before ordering and adjust the allowance if conditions differ from the plans.
For ready mix, use the result in cubic yards and confirm delivery quantities, order increments and minimum charges with the supplier. For bagged concrete, enter published mixed yield and round up to whole bags.
This is a quantity estimate. Footing dimensions, placement, reinforcement and concrete specification come from the approved project plans.
Multiply length, width and depth in feet. Apply your allowance, then divide by 27 to convert cubic feet to cubic yards.
Enter the inside diameter, then enter the depth of the concrete fill.
Calculate them as separate sections. Where they overlap, count the shared space only once.
The calculator divides the unrounded volume by the mixed yield. A partial bag in the estimate becomes a whole bag in the purchase quantity.
Use the dimensions specified for the project. This calculator estimates concrete quantity from dimensions you enter.
Calculate and record each group separately. Add the volumes before you finalize a common ready mix order or bag purchase.
It is an example input. Adjust it for the measured forms, uneven excavation and expected placement losses.
Measure across the inside of the tube and record the fill depth. Group identical tubes together. Confirm the planned bottom and top elevations before ordering.
Sketch the strip footing as separate straight runs. For overlapping corners, shorten one measured section by the shared length. Estimate any extra depth as a separate block.
Use published bag yield for the bag estimate. For ready mix, confirm the supplier’s minimum delivery and ordering increments. Compare total cost and placement logistics.